The third in the row pedestrian bridge of the Overall Program called “Construction of six (6) pedestrian Bridges in main roads in Attica area in Greece” took place with great success.–
Several installation methods due to space limitations and local traffic restrictions. The lifting method took place into two stages.
First stage: the placement of the deck in two segments which would be stand on a temporary scaffold at the mid of its span.
Duration: 6 hours including mobile cranes set up.
Second stage: the placement of the arch in two segments which would be stand on temporary bracings.
Duration: 8 hours including mobile cranes set up.
Special specifications: a. 100% Certificate Welding Checks on factory and on-site b. High requirements for Construction and for the Installation part